Labor waste in housing construction projects: an empirical study

journal contribution
posted on 2021-01-01, 00:00 authored by S Nassri, S Talebi, F Elghaish, K Koohestani, S McIlwaine, M. Reza Hosseini, M Poshdar, M Kagioglou

Purpose
High-level labor waste is a major challenge in construction projects. This paper aims to identify, quantify and categorize labor waste in the context of Iranian housing construction projects.


Design/methodology/approach
This research uses a case study approach, with empirical data collected through direct observations and semi-structured interviews.


Findings
Having triangulated the findings from the literature review and empirical studies, a list of eight types of waste was derived for the thirteen observed laborers in ten case study projects. The empirical studies allowed the labor waste identified from the literature to be verified and refined by considering it in the context of the observed activities, and led to two new types of waste being identified which were not considered in the literature. Findings indicate that nearly 62% of laborers' time is spent on non-value-adding activities. It appeared that “unnecessary movement,” “waiting” and “indirect work” make up the highest labor waste.


Research limitations/implications
This research focuses only on onsite resource flows in a housing construction site. It does not include offsite flows such as material delivery to site.


Originality/value
The findings have provided substantial evidence on type and amount of labor waste and provide a solid basis to stimulate construction actors to participate in reducing labor waste and improving productivity.

History

Journal

Smart and Sustainable Built Environment

Pagination

1 - 16

Publisher

Emerald

Location

Bingley, Eng.

ISSN

2046-6099

eISSN

2046-6102

Language

English

Publication classification

C1 Refereed article in a scholarly journal

Usage metrics

    Research Publications

    Categories

    No categories selected

    Exports

    RefWorks
    BibTeX
    Ref. manager
    Endnote
    DataCite
    NLM
    DC