Minimizing Cost Overrun in Rail Projects through 5D-BIM: A Conceptual Governance Framework

journal contribution
posted on 2024-03-12, 02:45 authored by OAI Hussain, RC Moehler, SDC Walsh, Dominic Doe Ahiaga-DagbuiDominic Doe Ahiaga-Dagbui
Integration of 5D Building Information Modeling (BIM) into large rail projects has the potential to significantly enhance cost management and control. Nevertheless, 5D-BIM implementation has encountered difficulties stemming from technical, functional, and governance-related factors. This paper builds a conceptual framework to support financial decision making, enhances project management, and promotes efficient project delivery. The framework encompasses a set of interrelated elements that include project governance, BIM policies and standards, digital platforms, BIM LOD, cost-estimation classification, and continuous improvement. The proposed framework acknowledges the significance of project governance in guiding and organizing the implementation of 5D-BIM. Additionally, BIM policies and standards ensure the adherence to quality standards for the produced BIM models. Digital platforms serve as the basis for multiple users to generate, access, share, and exchange project information. BIM LOD promotes collaboration and coordination among all project stakeholders. Cost-estimation classification aligns the estimation process with the development of project scope and financial decision making. Continuous improvement plays a vital role in optimizing processes, enhancing efficiency, and achieving higher-quality outcomes. Moreover, it fosters stakeholder satisfaction, improves project performance, and nurtures a conducive environment for innovation and learning. The study analyzes the framework utilization in Victorian rail projects and identifies key implementation challenges. The main technical hurdles encountered were the lack of current horizontal infrastructure standards for data exchange and the lack of compatibility with current cost-management standards. Increased project complexity and the absence of clear project governance strategies and processes also posed organizational challenges. A further validation of the framework in real-world rail projects was recommended to achieve the implementation goals.

History

Journal

Buildings

Volume

14

Article number

478

Pagination

1-33

Location

Basel, Switzerland

ISSN

2075-5309

eISSN

2075-5309

Language

eng

Publication classification

C1 Refereed article in a scholarly journal

Issue

2

Publisher

MDPI

Usage metrics

    Research Publications

    Exports

    RefWorks
    BibTeX
    Ref. manager
    Endnote
    DataCite
    NLM
    DC