AND SEWERAGE TRUST


THE O



OPENING



BY

The Hon. CLIVE PHILLIP STONEHAM. m.la

(MINISTER OF WATER SUPPLY)

At Ballan. Victoria

December 15th, 1954

Geelong Waterworks and Sewerage

Trust

PROGRAMME

15/12/1954

SPEAKERS:

Cr. W. H. EOFPEY

President, Shire of Ballan.

Mr. J. W. CARR

Chairman, Geelong Waterworks and Sewerage Trust.

Mr. J. M. MACINTYRE

Engineer-in-Chief, Geelong Waterworks and Sewerage Trust. Mr. H. W. McCAY

Deputy Chairman, State Rivers and Water Supply Commission.

Mr. L. F. a D’ARCY, M.L.A.

The Hon. the Minister of Water Supply C. P. STONEHAM, Esq., M.L.A.

INSPECTION

AFTERNOON TEA

/

.


GEELONG WATERWORKS AND SEWERAGE TRUST

1908-1954

COMMISSIONERS

J. W. CARR, Esq., J.P., Chairman B. E. PURNELL, Esq., M.B.E., J.P., Vice-Chairman - City of Geelong F. H. WALLACE, Esq., O.B.E., J.P. - City of Geelong G. NEUNHOFFER, Esq. - City of Geelong West N. M. FREEMAN, Esq. - City of Newtown and Chilwell A. S. THOMSON, Esq. - Shire of Corio R. E. GORELL, Esq. - Shires of Bellarine and South Barwon

Engineer-in-Chief :    Secretary :

J. M. MACINTYRE, M.B.E., B.Sc., M.I.E., Aust.    B. C. HENSHAW, A.A.S.A., A.C.I.S.

Assistant Engineer-in-Chief :    Assistant Secretary :

A. W. COOKE, A.I.M.E. Aust.    S. W. BIRRELL

Project Superintendent - Bostock Reservoir :

V. SEITZ


mm

VIEWS OF SITE

PRIOR TO COMMENCEMENT

OF PROJECT

The proposal to construct a dam on the Eastern Moorabool River, below its junction with the Paddock Creek, was first made in 1923 by Mr. J. S. Sharland, who was then the Trust’s Engineer-in-Chief. Designs were prepared and approved by the Government and preparations were made to commence construction.

The Commissioners of the Trust decided to call the dam The Bostock Dam, in honour of Mr. T. E. Bostock, a former Mayor of the Town of Geelong and one of the prominent citizens who had been responsible for the formation of the Trust.

The construction of the Bellarine Water Supply System by the State Rivers and Water Supply Commission, however, caused commencement of work to be postponed, and the project remained in abeyance until it was revived in 1946 by the then Chairman of the Trust, Mr. N. M. Freeman.

/

The plans and proposals were re-examined by Mr. R. G. Pearce, Engineer-in-Chief, and a new site was decided upon, half a mile down-stream from the original site.

New designs were prepared and approved by the Government on 19th June, 1953.

A tunnel was first constructed, to divert river water away from the site of the dam. This was completed, and the river was diverted on 15th December, 1953.

On the same day excavation of the foundations of the main embankment in the river bed was started.

The main embankment attains a height of 84 feet at its maximum and is designed to impound 1,500,000,000 gallons.

The spillway capacity is 24,000 cusecs, while the aqueduct can transmit 5 million gallons of water per day from the dam to the city.


MOORABOOL RIVER IMPOUNDED


CONTRACTORS OFFICE & WORKSHOPS



CLAY EXCAVATED FOR SPILLWAY APPROACH AND USED IN EMBANKMENT CONSTRUCTION



si®


DIVERSION INLBT & CHAMBER


%


%


%



Access ROAD


DIVERSION

OUTLET


PRELIMINARY INVESTIGATIONS



INVESTIGATING BASALT OVERLYING SANDSTONE FORMATION FOR ROCK FILL


DIVERSION TUNNEL

CONTRACTORS—Sainrapt and Brice (Aust.) Pty. Ltd., Melbourne


Length of    Tunnel including Gallery.......-    930    feet

Volume of    Excavation for approaches    -------    11,500    cub.    yards

Volume of    Tunnel Excavation through    sandstone    and    shale    -    -    1,434    cub.    yards

Volume of    R. Concrete in Tunnel Lining.....-    -    1,113    cub.    yards

COST—£47,100


FLOOD DISCHARGE AFTER COMPLETION OF TUNNEL AND DURING CONSTRUCTION OF DAM


EXCAVATION OF TUNNEL ENTRANCE


FIRST STAGE OF CONSTRUCTION Clearing Site of Embankment

3rd STAGE

Concrete Core Wall Completed

Compacting Clay Inner Zone, Transition and Rock Zone Visible



4th STAGE

Bank at Full Supply Level showing Upstream Rip Rap


MAIN EMBANKMENT - SUBSIDIARY EMBANKMENT - SPILLWAY

CONTRACTOR—Thiess Bros. (Vic.) Pty. Ltd., Brisbane, Queensland

MAIN EMBANKMENT :

Volume of stripping from Embankment seat and quarries -    -

Volume of    clay in Inner    Zone -    --    --    --    -

Volume of sand in Transition Zone ------Volume of rockfill Zone (Sandstone) ______

Volume of Igneous Rock Rip-Rap ------Volume of concrete in cut off wall ------SUBSIDIARY EMBANKMENT :

Volume of stripping from Embankment seat -    -    -    -    -

Volume of    clay in Inner    Zone -    --    --    --    -

Volume of sand in Transition Zone ------Volume of Igneous Rock Rip-Rap ------SPILLWAY :

Volume of    excavation    -    --    --    --    --    -

Volume of concrete    ---------

COST—£110,000

64,200 cub. yds.

47,700 „

99

17,600 „

99

81,600 „

99

7,700 „

99

600 „

»

5,000 ..

20,000 „

99

2,000 „

99

3,000 „

99

78,000 „

99

1,600 „

99



PLACING

SUBSIDIARY EMBANKMENT INNER ZONE



OUTLET AQUEDUCT

CONTRACTORS—Messrs A. and F. McLean, Norlane, Geelong'


Length of pipes laid in trench    -    -    11,365    feet

Length of channel excavated -    -    -    21,000    feet

Length of tunnel excavated and    lined    -    1,496    feet

Volume of concrete in structures    -    -    300    cub.    yds.

Length of fencing along channel

section -------    42,000 feet

COST—£60,750

CHANNEL EXCAVATION AND PIPES AT TUNNEL APPROACH

Supply of Pipes and Fittings

CONTRACTOR—Humes Limited, 114 King Street, Melbourne



Length of    30    inch diameter R.C.    Pipes.....-    -    -    -

Length of 24 inch diameter R.C. Pipes -    --    --    --    -

Length of 21 inch diameter R.C. Pipes --------Length of    21    inch diameter Steel    Concrete    Lined    Pipes    -    -    -    -    -

Length of    15    inch diameter Steel    Concrete    Lined    Pipes    -    -    -    -    -

Number of special steel fittings -----------

Valves—2 only 18 inch diameter :

1 only 12 inch diameter......-----


400 feet 2,200 feet 7,900 feet 1,056 feet 100 feet 56 No.

3 No.


All pipes and fittings fabricated by Humes Ltd. 18 inch diameter valves were made by Orton and Burns Pty. Ltd., Melbourne, whilst the 12 inch diameter valve was made by M. B. John Ltd., Ballarat.


COST—£21,550


Raising of Road Bridge—Western Highway

AT PADDOCK CREEK



No. 2 SIPHON BOSTOCK AQUEDUCT


WORK EXECUTED BY—Country Roads Board of Victoria COST—£10,100


Costs of Project Stages

1.    Supply of Pipes    -    --    --    --    --    --    £21,550

2.    Construction of Bostock Aqueduct    -------    £60,750

3.    Diversion Tunnel    -    --    --    --    --    --    £47,100

4.    Construction of Main Embankment, Sudsidiary Embankment and

Spillway -----------    £110,000

5.    Raising of Highway Bridge over Paddock Creek -----    £10,100

6.    Acquisition of Land    £24,000

7.    Cement, Fencing Materials, Electrical Installation, Reinforcing Steel

and other items supplied on site by Trust -----    £17,500

8.    Preliminary Investigations, Engineering Surveys, Borings, Designs,

Fees, Supervision and Administration -    -    -    -    -    £21,000

£312,000


TOTAL EXPENDITURE

1